Project Site

Installation of Rapidwall®

The installation of Rapidwall® panels on-site involves a series of carefully coordinated steps, ensuring that the panels are correctly assembled, securely fixed, and integrated into the building structure. This process requires close collaboration between the logistics team, contractors, and site personnel.Installation process for Rapidwall® panels:

Process for Rapidwall® panels:

  • 1
    Site Preparation: Surveying the site, checking the foundation, installation of Starter/Dowel bars and marking panel positions.
  • 2
    Unloading and Inspection: Safe unloading, inspection of panels, and organizing installation accessories.
  • 3
    Panel Lifting: Using mobile cranes and lifting accessories such as Lifting Jaw to position Rapidwall® wall panels and slabs panels
  • 4
    Securing Panels: Fixing the panels securely to the foundation accessories such as multidirectional Wall Props & Jacks
  • 5
    Joining Panels: Aligning and securing panels together, ensuring weatherproof seals.
  • 6
    Integration: Installing lintels in cut out openings of doors & windows, Installation electrical, plumbing, or HVAC components.
  • 7
    Reinforcement: Rapidwall® slab cavities are reinforced with steel.
  • 8
    Concrete Casting: Casting of Wall & slab panels with concrete to achieve load bearing system.
  • 9
    Quality Control: Ongoing inspections to ensure proper installation and adjustments.
  • 10
    Post-Installation: Monitoring and addressing any issues after installation is complete

Starter Bars

Slab installation

Wall Panel Installation

Embeded Beams

Doors & Windows cut-out

Electrical coordination

Concreting

Finishing treatment